TM 1-1520-238-23
Change 1 9-145
9.41.
BATTERY RELAY REMOVAL/INSTALLATION continued
b. Remove relay (3) from aft avionics bay bulk-
head (20).
(1) Remove two screws (21) and four washers
(22).
(2) Remove relay (3).
9.41.4. Cleaning
a. Clean removed and attaching parts (para
1.47).
9.41.5. Inspection
a. Check removed and attaching parts for dam-
age (para 9.1).
b. Check wires for wear, cuts, breaks, and dam-
aged terminal lugs (para 9.1).
c. Check removed and attaching parts for corro-
sion (para 1.49).
9.41.6. Installation
a. Install relay (3) on bulkhead (20).
(1) Position relay (3) on bulkhead (20).
(2) Install two screws (21) and four washers (22).
b. Perform
electrical
bond
check
(TM 55-1500-323-24).
(1) Bond shall be 0.1 OHM or less. Use
ohmmeter.
GO TO NEXT PAGE
20
22
21
3
M04-1135-5A
20
22
21
3
M04-1135-6A