MOORING PAVED SURFACE continued
b. Chain installation.
(1) Install the hooks (4) of the forward mooring
chains (5) into the aircraft mooring rings (2).
(2) Adjust the chains (5) with the chain adjuster
(6). Mooring chains (5) and chain adjusters
(6) are provided at each of the mooring points
(3) on the mooring pad (1).
(3) Chains (5) should be adjusted to the point
where slack has been removed.
(4) Repeat this procedure for the four aft mooring
chains (7).
(5) All chains (7) will hook into the mooring ring
(8) located on the lower surface of the tail-
boom at F.S. 450.