TM 1-1520-238-23
1-286
1.91.
HOISTING - MAIN TRANSMISSION REMOVAL
1.91.1. Removal
WARNING
Hoisted components can cause injury
or death if they fall. Keep away from
hoisted components and loaded
crane. If injury occurs, seek medical
aid.
a. Position crane hook (1) over installed trans-
mission sling (2).
(1) Rotate crane handle (3) to up position to al-
low lateral movement of crane boom arm (4).
(2) Use two tag lines (5) to move boom arm (4).
(3) Turn boom arm (4) to aline hook (1) over sling
shackle (6).
(4) Rotate handle (3) to down position to prevent
lateral movement of boom arm (4).
CAUTION
To prevent crossing cable on spool and
damage to crank, tension must be ap-
plied when letting out or taking in cable.
b. Insert hook (1) into shackle (6).
(1) Crank winch (7) to position hook (1) below
shackle (6).
(2) Snap hook (1) into shackle (6).
(3) Crank winch (7) to remove cable slack.
GO TO NEXT PAGE
2
1
6
M04-2248-1
4
5
7
3