TM 1-1520-238-23
2-155
2.54.
CPG STATION ACCESS DOOR REMOVAL/INSTALLATION continued
2.54.6. Installation
a. Position door (13) in access opening.
(1) Install two hinge pins (12) in hinge halves (9)
and (10).
NOTE
If installing original door, perform step
i.
If installing replacement door, perform
step b.
If interference contact between hinge
halves exists, perform step d.
b. Secure door cylinder assembly (para 2.59).
c. Loosen lower hinge bolts (14) to allow move-
ment of door (13).
d. If required, relieve interference between hinge
halves and bow beam (para 2.59).
e. Position door (13) to float on rubber seal in
opening. Remove any contact between door (13)
bumper and airframe bumper (para 2.59).
NOTE
Minimum gap between door skin and air-
frame is 0.030 INCH.
f. If required, trim door skin to obtain acceptable
gap.
NOTE
Lower hinge bolts must be removed,
cleaned, and new sealant applied before
installation.
g. Install lower hinge bolts (para 2.58).
h. Release door cylinder assembly (para 2.59).
i. Install two new cotter pins (11).
GO TO NEXT PAGE
10
9
11
12
14
M04-1438-5
13
10
9
11
12
14