TM 1-1520-238-23
3-95
3.26.
MAIN LANDING GEAR CABLE CUTTER REMOVAL/INSTALLATION continued
b. Install clamp halves (1) and (2) on trailing arm
(3) and cutter (12).
(1) Apply tape to inner mating surfaces of clamp
halves (1) and (2). Use tape (item 206,
App F).
(2) Position clamp halves (1) and (2) on trailing
arm (3) with chamfered edges (20) facing in-
board, and alined.
(3) Install two bolts (10) and washers (11)
through clamp halves (1) and (2).
(4) Install washers (9) and nuts (8). Do not tight-
en.
(5) Install two bolts (6) and washers (7) through
aft clamp half (1) and cutter (12).
(6) Install washers (5) and nuts (4) on bolts (6).
(7) Tighten all nuts previously installed and install
cotter pin (13). Ensure clamp halves (1) and
(2) alinement is maintained.
(8) Seal around edges of clamp halves (1) and
(2). Use sealing compound (item 177, App F)
and brush (item 34, App F).
c. Inspect (QA).
END OF TASK
4
6
12
7
5
2
11
10
20
9
8
1
3
13
M04-3533-6