TM 1-1520-238-23
2-400
Change 4
2.110.
VERTICAL STABILIZER TIP FAIRINGS T545A AND T545 REMOVAL/INSTALLATION continued
b. Pin four identified wires (9) in four splices (10)
(TM 55-1500-323-24).
c. Install clamp (5) to fairing (2).
(1) Install screw (6) through washer (7), clamp
(5), spacer (8), and clamp stackup (18).
d. Install clamp (1) on fairing (2).
(1) Position two splices (10) in clamp (1).
(2) Install screw (3) through washer (4) and
clamp (1).
e. Inspect (QA).
f. Connect aft radar warning receiver
(TM 11-1520-238-23-1).
g. Connect global positioning antenna (ADD)
(TM 11-1520-238-23-1).
h. Perform spiral antenna and radar warning
maintenance
operational
check
(TM 11-1520-238-23-2).
i. Perform navigation and formation lights main-
tenance operational check (TM 1-1520-238-T).