3.3.
MAIN LANDING GEAR UPPER STRUCTURAL SUPPORT REMOVAL/INSTALLATION continued
3.3.3. Removal
a. Remove upper structural support (1) from
cable cutter (2).
(1) Hold six screws (3). Remove six self-locking
nuts (4) and washers (5).
(2) Remove six screws (3).
(3) Remove support (1) from cutter (2).
3.3.4. Cleaning
a. Wipe removed and attaching parts with a
clean rag.
3.3.5. Inspection
a. Check attachment area for wear, elongation of
holes, and cracks. None allowed.
b. Check components for corrosion (para 1.49).
3.3.6. Installation
a. Install support (1) on cutter (2).
(1) Position support (1) on cutter (2).
(2) Aline support (1) with six mounting holes on
cutter (2).
(3) Install six screws (3).
(4) Hold six screws (1). Install six washers (5)
and nuts (4).
b. Inspect (QA).
c. Install main landing gear cable cutter (para
3.26).
END OF TASK