TM 1-1520-238-23
4-488
4.148.
NO. 2 ENGINE POWER AVAILABLE SPINDLE CENTER CABLE INSTALLATION continued
x. Install clamp (67) on clamp (68).
(1) Position clamp (67) on cable (2).
(2) Install screw (69) through washer (70),
clamps (68) and (67), washer (71), and nut
(72).
y. Install clamp (73) on clamp (74).
(1) Position clamp (72) on cable (2).
(2) Install screw (75) through washer (76), clamp
(73), spacer (77), clamp (74), washer (78),
and nut (79).
z. Install clamps (80) and (81) on bracket (82).
(1) Position clamp (80) on cable (2).
(2) Install screw (83) through washer (84), brack-
et (82), clamps (80) and (81), washer (85)
and nut (86).
aa. Perform No. 2 engine power available spindle
system rigging check (para 4.187).
ab. Install transformer-rectifier No. 1 (para 9.30).
ac. Install pilot FUEL control panel (para 10.54).
ad. Install pilot EXT LT/INTR LT panel (para 9.62).
ae. Install access panels L160 and L200, console
panels PL1 and PL3; secure doors T250L,
T250R, T290L, T290R, and L325 (para 2.2).
af. Inspect (QA).
ag. Perform power plants maintenance operation-
al check (engine 2) (TM 1-1520-238-T).
END OF TASK
M04-1186-24
72
71
67
2
68
70
69
77
2
76
73
M04-1186-25
75
74
78
79
81
86
2
M04-1186-27
84
83
82
85
80