TM 1-1520-238-23
9-96.4
Change 6
9.26.
AC GENERATOR NO. 1 REMOVAL/INSTALLATION continued
k. Install four wires (6) on generator (2).
(1) Install four identified wires (6), terminal lugs
(8), and locknuts (7) on terminal studs (9).
l. Install terminal cover (1) on generator (2).
(1) Position cover (1) on generator (2).
(2) Apply primer to threads of two screws (3).
Use primer coating (item 147, App F).
(3) Install two flat washers (5), lockwashers (4),
and screws (3).
m. Attach connectors P3 (10) and P2 (11) to gen-
erator (2).
(1) Attach connector P3 (10) to receptacle J1
(12).
(2) Attach connector P2 (11) to receptacle J2
(13).
n. Inspect (QA).
o. Perform AC electrical power generation main-
tenance operational check (TM 1-1520-238-T).
p. Install access panel L200 (para 2.2).
END OF TASK
M04-1089-8A
2
6
7
8
9
M04-1089-9
1
2
3
4
5
2
10
11
12
13
M04-1089-10