TM 1-1520-238-23
9-567
9.149.
SQUAT SWITCH TARGET PLATE ADJUSTMENT
9.149.1. Description
This task covers:
Removal. Adjustment. Installation.
9.149.2. Initial Setup
Tools:
Electrical tool kit (item 378, App H)
0.0015 - 0.0250-inch thickness gage (item 152, App H)
Materials/Parts:
Wire (item 226, App F)
Personnel Required:
68X
Armament/Electrical System Repairer
68X3F
Armament/Electrical System Repairer/
Technical Inspector
References:
TM 11-1520-238-23-2
Equipment Conditions:
Ref
Condition
1.57
Helicopter safed
2.2
Fairing L140 removed
1.66
Helicopter on jacks
9.149.3. Removal
a. Measure clearance A between top of target
plate (1) and bottom of squat switch (2).
(1) Clearance must be 0.150 to 0.190 INCH. Use
thickness gage.
b. Lower helicopter to ground (para 1.66).
GO TO NEXT PAGE
M04-3010-1
2
1
M04-3010-2
A