TM 1-1520-238-23
4-636
4.181.
NO. 2 ENGINE LOAD DEMAND SPINDLE/POWER AVAILABLE SPINDLE AFT CABLE SPRING
TENSION CLIP REMOVAL/INSTALLATION continued
4.181.4. Cleaning
a. Clean removed and attaching parts (para
1.47).
4.181.5. Inspection
a. Check spring tension clip assembly for
cracks. None allowed.
b. Check spring tension clip assembly for corro-
sion (para 1.49).
c. Check spring tension clip assembly for loose
or missing rivets (TM 1-1500-204-23). None al-
lowed.
4.181.6. Installation
a. Install spring tension clip assembly (5) on na-
celle firewall channel (6).
(1) Install two screws (7) through clip assembly
(5), spacers (10), and channel (6).
(2) Install two washers (9) and nuts (8) on screws
(7).
b. Attach connectors P24 (2) and P22 (1).
(1) Attach connector P24 (2) to receptacle J24
(4).
(2) Attach connector P22 (1) to receptacle J22
(3).
c. Inspect (QA).
d. Secure access door RN1 (para 2.2).
END OF TASK
M04-3931-4
5
7
6
10
8
9
1
3
2
M04-3931-5
4