TM 1-1520-238-23
4-640
4.182.
NO. 1 ENGINE POWER AVAILABLE SPINDLE (PAS) RIGGING PROCEDURE continued
f. Install 3 rig pin (8) fully in bracket (9) and
bellcranks (10) and (11).
NOTE
If bellcrank does not aline, go to step g. If
bellcrank alines, go to step l.
g. Adjust No. 1 power quadrant connnecting link
(12) to aline with bellcrank (11).
(1) Remove and discard cotter pin (13).
(2) Hold bolt (14). Remove nut (15).
(3) Remove bolt (14) from bellcrank (11) and link
(12).
(4) Remove lockwire from link (12).
(5) Loosen two jam nuts (16) at ends of link (12).
(6) Adjust length of link (12) as needed. Aline link
rod end (17) with bellcrank (11).
h. Install link (12) on bellcrank (11). Torque nut
(15) 14 to 18 INCH-POUNDS. Torque two jam
nuts (16) to 25 INCH-POUNDS.
(1) Install bolt (14) through bellcrank (11) and rod
end (17).
(2) Install nut (15) on bolt (14).
(3) Hold bolt (14). Torque nut (15) to 14 INCH-
POUNDS. Use torque wrench.
(4) Increase torque to aline cotter pin hole, but do
not exceed 18 INCH-POUNDS.
(5) Install new cotter pin (13).
(6) Torque two jam nuts (16) to 25 INCH-
POUNDS. Use torque wrench.
(7) Lockwire two jam nuts (16) to link (12). Use
wire (item 226, App F).