TM 1-1520-238-23
4-512
4.154.
ENGINE LOAD DEMAND SPINDLE BELLCRANK REMOVAL/INSTALLATION continued
b. Install control rod (12) on bellcrank (2). Torque
nut (15) 14 to 18 INCH-POUNDS.
(1) Position rod end (16) in bellcrank (2).
(2) Install bolt (14) through bellcrank (2) and rod
end (16).
(3) Install nut (15) on bolt (14). Torque nut (15) to
14 INCH-POUNDS. Use torque wrench.
(4) Increase torque to aline cotter pin hole, but do
not exceed 18 INCH-POUNDS.
(5) Install new cotter pin (13).
c. Install cable (7) on bellcrank (2). Torque nut
(10) 14 to 18 INCH-POUNDS.
(1) Position rod end (11) in bellcrank (2).
(2) Install bolt (9) through bellcrank (2) and rod
end (11).
(3) Install nut (10) on bolt (9). Torque nut (10) to
14 INCH-POUNDS. Use torque wrench.
(4) Increase torque to aline cotter pin hole, but do
not exceed 18 INCH-POUNDS.
(5) Install new cotter pin (8).
GO TO NEXT PAGE
13
15
16
14
2
12
M04-2317-8
7
10
2
M04-2317-9
8
9
11