TM 1-1520-238-23
4-517
4.156.
ENGINE LOAD DEMAND SPINDLE BELLCRANK SUPPORT
REMOVAL/INSTALLATION continued
4.156.3. Removal
a. Remove support (1) from deck (2).
(1) Remove four bolts (3) and washers (4) from
support (1) and deck (2).
(2) Remove support (1).
4.156.4. Cleaning
a. Clean support mounting area on deck (para
1.47).
4.156.5. Inspection
a. Check support for cracks. None allowed.
b. Check support mounting area on deck for
cracks. None allowed.
c. Check deck and support for corrosion (para
1.49).
4.156.6. Installation
a. Install support (1) on deck (2).
(1) Install four bolts (3) through washers (4) and
support (1) into deck (2).
b. Inspect (QA).
c. Install engine load demand spindle bellcrank
(para 4.154).
END OF TASK
M04-2318-2
3
4
1
2