TM 1-1520-238-23
9-116
9.32.
TRANSFORMER-RECTIFIER NO. 2 REMOVAL/INSTALLATION continued
9.32.5. Inspection
a. Check for missing or damaged nutplates (para
9.1).
b. Check removed and attaching parts for dam-
age (para 9.1).
c. Check wires for wear, cuts, breaks, and dam-
aged terminal lugs (para 9.1).
d. Check connector for cracks, broken connec-
tions, bent pins, or damaged threads (para
9.1).
e. Check removed and attaching parts for corro-
sion (para 1.49).
9.32.6. Installation
a. Install transformer-rectifier (2) on mount (14).
(1) Position transformer-rectifier (2) on mount
(14).
(2) Install two aft bolts (15) and washers (16).
(3) Install two forward bolts (15) and washers
(16).
b. Perform
electrical
bonding
check
(TM 55-1500-323-24).
(1) Bond shall be 0.0025 OHM or less. Use
ohmmeter.
c. Install clamp block (9) on hydraulic lines (10)
and servoactuator (11).
(1) Position clamp block (9) on lines (10).
(2) Install hex screw (12) through washer (13),
and clamp block (9), into servoactuator (11).
GO TO NEXT PAGE
2
M04-1097-5
15
16
14
13
12
11
10
9
M04-1097-11