TM 1-1520-238-23
11-364
11.83.
CPG CYCLIC STICK HOUSING LATERAL SHEAR PIN REPLACEMENT continued
d. Install link (1) on arm (2). Torque nut (4) 30 to 40
INCH-POUNDS.
(1) Install bushing (6) in arm (2).
(2) Install bolt (5) through bushing (6), arm (2),
and link (1).
(3) Check fit of self-retaining bolt (5) (para 11.1).
(4) Install nut (4). Torque nut (4) to 30 INCH-
POUNDS. Use torque wrench.
(5) Increase torque to aline cotter pin hole, but do
not exceed 40 INCH-POUNDS.
(6) Install new cotter pin (3).
e. Inspect (QA).
f. Perform flight control system maintenance
operational check (TM 1-1520-238-T).
g. Perform DASE maintenance operational
check (TM 1-1520-238-T).
h. Install CPG cyclic stick cover (para 11.65).
i. Install access door B60 (para 2.2).
j. Inspect (QA).