CPG ENGINE FIRE PULL SWITCH REMOVAL/INSTALLATION - continued
c. Attach two identified wires (11) to wires (12).
(1) Install
two
new
splices
(13)
(TM 55-1500-323-24).
d. Install switch (5) on panel (2).
(1) Position switch (5) on panel (2).
(2) Install two screws (7).
e. Install handle (4) on switch (5).
(1) Install handle (4) on switch (5).
(2) Install screw (6).
(3) Push handle (4) to retracted position.
f. Install panel (1) on panel (2).
(1) Install five screws (3).
g. Inspect (QA).
h. Install CPG fire bottle select switch light indi-
cating panel (para 12.37).
i. Perform fire extinguishers maintenance op-
erational check (TM 1-1520-238-T).
END OF TASK
11
M04-986-8
13
13
12
2
5
M04-986-9
7
M04-986-10
4
6
5
10
M04-986-1 1
3
1
2