8.38.
PITOT STATIC SYSTEM TUBING TRANSITION REPLACEMENT
8.38.1. Description
This task covers:
Removal. Inspection. Installation.
8.38.2. Initial Setup
Tools:
Aircraft mechanics tool kit (item 376, App H)
Light duty laboratory apron (item 27, App H)
Chemical protective gloves (item 154, App H)
Heat protective gloves (item 155, App H)
Electric gun type heater (item 163, App H)
Adjustable air filtering respirator (item 262, App H)
Materials/Parts:
Adhesive (item 9, App F)
Cloth (item 48, App F)
Cloth (item 52, App F)
Marker (item 123, App F)
Methyl ethyl ketone (item 124, App F)
Personnel Required:
67R
Attack Helicopter Repairer
67R3F
Attack Helicopter Repairer/Technical
Inspector
References:
TM 1-1500-204-23
Equipment Conditions:
Ref
Condition
1.57
Helicopter safed