TM 1-1520-238-23
9-39
9.10.
ELECTRICAL POWER DISTRIBUTION BOX RELAY COVER REMOVAL/INSTALLATION
9.10.1. Description
This task covers:
Removal. Cleaning. Inspection. Installation.
9.10.2. Initial Setup
Tools:
Aircraft mechanics tool kit (item 376, App H)
Light duty laboratory apron (item 27, App H)
Chemical protective gloves (item 154, App H)
Industrial goggles (item 156, App H)
1 1/4-inch blade putty knife (item 199, App H)
Adjustable air filtering respirator (item 262, App H)
Materials/Parts:
Gasket (table D-73 or figure D-52, App D)
Adhesive (item 18, App F)
Brush (item 34, App F)
Strap (item 191, App F)
Personnel Required:
67R
Attack Helicopter Repairer
67R3F
Attack Helicopter Repairer/Technical
Inspector
References:
TM 1-1520-238-T
TM 55-1500-323-24
Equipment Conditions:
Ref
Condition
1.57
Helicopter safed
9.10.3. Removal
a. Enter pilot station (para 1.56). Observe all
safety precautions.
b. On pilot aft circuit breaker panel, open AFT
FAN circuit breaker.