11.145. CPG DIRECTIONAL SHEAR PIN ACTIVATED DECOUPLER (SPAD) INSTALLATION continued
11.145.3. Installation
a. Install SPAD (1) on mounting bracket (2).
Torque nut (3) 30 to 40 INCH-POUNDS.
(1) Position SPAD (1) on bracket (2) with swivel
arm (4) to left.
(2) Install bolt (5) through washer (6) into shaft
(7).
(3) Install shaft (7) with bolt (5) and washer (6)
through bracket (2) and SPAD (1).
(4) Install retainer (8).
(5) Check fit of self-retaining bolt (5) (para 11.1).
(6) Install nut (3). Torque nut (3) to 30 INCH-
POUNDS. Use torque wrench.
(7) Increase torque to aline cotter pin hole, but do
not exceed 40 INCH-POUNDS.
(8) Install new cotter pin (9).